ADVANCED FIBER RESPONSE INC | Public Works | Contractor services | EMERGENCY REPAIR TO CABLE | 3/24/2010 | $725.60 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Splicing of Fiber Optic Cable | 8/9/2010 | $2,766.84 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Emergency Rpr of Fiber Optic | 10/5/2010 | $196.33 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Repair to fiber optic cable | 10/28/2010 | $1,385.38 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Fiber splice into CDOT Fiber | 12/3/2010 | $480.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Install Splice Point | 3/31/2011 | $1,168.29 |
ADVANCED FIBER RESPONSE INC | Public Works | Construc Costs-Sidewalks | Relocate handhole-Alameda/Hoyt | 5/3/2011 | $1,660.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Emer Repair of Fiber Optic | 12/9/2011 | $2,213.16 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | 4 Man Splice Crew 1/13/12 cut | 4/4/2012 | $2,900.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Construc Costs-Streets/Roadway | KIPLING & COLFAX CABINET WORK | 6/15/2012 | $760.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Construc Costs-Traffic Signals | SIGNAL WORK KIPLING/EXPOSITION | 8/10/2012 | $680.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | Bear Creek Traffic Cabinet Rpr | 10/16/2012 | $1,020.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Contractor services | New Camera at Kipling/Alameda | 2/28/2013 | $900.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | SPLICE CREW TROUBLESHOOT | 10/24/2013 | $190.00 |
ADVANCED FIBER RESPONSE INC | Public Works | Other profess & tech services | fiber splicing on IP cameras | 5/1/2014 | $3,420.00 |