Community Resources | Consulting services-Bldg Const | SLATERPAULL | Carmody Pool Add'l Work | | 1/13/2010 | $3,100.00 |
Community Resources | Consulting services-Bldg Const | SLATERPAULL | Carmody Pool Add'l Work | | 1/13/2010 | $1,451.00 |
Community Resources | Consulting services-Bldg Const | FOOTHILLS ROOF SERVICES INC | Roof consulting services | | 1/14/2010 | $260.00 |
Community Resources | Consulting services-Bldg Const | THE BRENDLE GROUP INC | RFD Deve Energy Feasibity Stud | | 2/17/2010 | $500.00 |
Community Resources | Consulting services-Bldg Const | SPEEDY MESSENGER DEL SERV | 2009 messenger service for CR | | 2/19/2010 | $15.93 |
Community Resources | Consulting services-Bldg Const | C4I DESIGN GROUP INC | Architect & Engineer Services | | 2/25/2010 | $4,366.80 |
Community Resources | Consulting services-Bldg Const | C4I DESIGN GROUP INC | Design Svc for Maint Shops | | 3/18/2010 | $3,632.90 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | Comprehensive Asbestos Survey- | | 3/18/2010 | $953.40 |
Community Resources | Consulting services-Bldg Const | TANDUS US INC | LHC Offices - Carpet | | 3/31/2010 | $2,448.15 |
Community Resources | Consulting services-Bldg Const | TANDUS US INC | LHC Offices - Carpet | | 4/15/2010 | $3,912.38 |
Community Resources | Consulting services-Bldg Const | C4I DESIGN GROUP INC | Archit & Eng Design Svcs-Waste | | 4/29/2010 | $641.10 |
Community Resources | Consulting services-Bldg Const | C4I DESIGN GROUP INC | Archt & Eng Design Svcs | | 4/29/2010 | $7,647.40 |
Community Resources | Consulting services-Bldg Const | EWERS ARCHITECTURE | Design Services Motel Move | | 5/6/2010 | $4,375.00 |
Community Resources | Consulting services-Bldg Const | MARTIN MARTIN INC | Head Start - Engineering Serv | | 7/28/2010 | $650.00 |
Community Resources | Consulting services-Bldg Const | C4I DESIGN GROUP INC | Architectural & Engineer | | 7/29/2010 | $795.80 |
Community Resources | Consulting services-Bldg Const | BIRDI DISC GOLF | Site Evaluation for Disc Golf | | 8/4/2010 | $1,950.00 |
Community Resources | Consulting services-Bldg Const | INDOX SERVICES | Estes Motel Prints & Mylars | | 8/25/2010 | $44.82 |
Community Resources | Consulting services-Bldg Const | EWERS ARCHITECTURE | Design Services Motel Move | | 11/9/2010 | $1,625.00 |
Community Resources | Consulting services-Bldg Const | EWERS ARCHITECTURE | Design Services Motel Move | | 11/9/2010 | $31.00 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | 9700 W Colfax Ave - Comprehens | | 11/22/2010 | $635.00 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | Estes Motel - Concrete Samplin | | 12/20/2010 | $570.00 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | Estes Motel - Pier Observation | | 12/20/2010 | $671.00 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | Estes Motel - Compaction Testi | | 12/20/2010 | $420.00 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | Estes Motel - Concrete Samplin | | 12/31/2010 | $110.00 |
Community Resources | Consulting services-Bldg Const | A G WASSENAAR INC | 9700 W Colfax - Comprehensive | | 12/31/2010 | $295.00 |
Community Resources | Consulting services-Bldg Const | WALKER CONSULTANTS INC | Civic Center Plaza - Update of | | 6/1/2011 | $2,000.00 |
Community Resources | Consulting services-Bldg Const | WALKER CONSULTANTS INC | Prof Services - Construction | | 6/1/2011 | $500.00 |
Community Resources | Consulting services-Bldg Const | WALKER CONSULTANTS INC | Prof Services - Construction | | 8/4/2011 | $1,000.00 |
Community Resources | Consulting services-Bldg Const | WALKER CONSULTANTS INC | Prof Services - Construction | | 8/25/2011 | $1,604.34 |
Community Resources | Consulting services-Bldg Const | WALKER CONSULTANTS INC | Prof Services - Construction | | 9/22/2011 | $757.44 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | Corrected Acct # | | 6/9/2015 | $18,722.50 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | Corrected Acct # | | 7/22/2015 | $19,256.76 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | Corrected Acct # | | 9/10/2015 | $2,601.23 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | CO #1 Add'l Design Svcs | | 10/8/2015 | $3,398.14 |
Community Resources | Consulting services-Bldg Const | THE BALLARD GROUP INC | Link Pool - Mechanical Upgrade | | 10/13/2015 | $1,030.08 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | Corrected Acct # | | 11/10/2015 | $1,411.85 |
Community Resources | Consulting services-Bldg Const | THE BALLARD GROUP INC | Link Pool - Mechanical Upgrade | | 12/15/2015 | $1,545.12 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | Corrected Acct # | | 12/15/2015 | $26.39 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | CO #1 Add'l Design Svcs | | 12/15/2015 | $366.40 |
Community Resources | Consulting services-Bldg Const | BARKER RINKER SEACAT ARCHITECTURE | CO #2 Phase II Add'l Svcs | | 12/15/2015 | $1,920.17 |