Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 7/7/2010 | $6,533.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 8/11/2010 | $364.50 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 10/7/2010 | $3,179.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 11/9/2010 | $2,727.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 12/9/2010 | $226.50 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 12/9/2010 | $1,183.30 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Proposed Water Ski Ramp - Soil | | 12/20/2010 | $650.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 1/13/2011 | $925.35 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 2/14/2011 | $1,267.85 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 3/9/2011 | $1,344.85 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 4/7/2011 | $580.50 |
Community Resources | Consulting Costs-Other Improve | DENVER NEWSPAPER AGENCY (REMIT TO) | CR Dry Gulch | | 4/14/2011 | $172.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 6/8/2011 | $204.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 7/13/2011 | $1,474.15 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 7/13/2011 | $1,572.85 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 8/4/2011 | $3,579.67 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 9/14/2011 | $1,300.16 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 10/6/2011 | $598.12 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Holbrook Park Lower Pond | | 11/10/2011 | $479.20 |
Community Resources | Consulting Costs-Other Improve | DLT SOLUTIONS | Autocad upgrade PO #1432 | | 12/31/2011 | $4,788.00 |
Community Resources | Consulting Costs-Other Improve | SOUTH PLATTE WETLANDS INC | .06 Acre Wetland Mitigations | | 4/4/2012 | $4,000.00 |
Community Resources | Consulting Costs-Other Improve | DENVER NEWSPAPER AGENCY (REMIT TO) | Dry Culch | | 5/10/2012 | $86.00 |
Community Resources | Consulting Costs-Other Improve | WALKER CONSULTANTS INC | Civic Center - Plaza and | | 7/26/2012 | $2,920.00 |
Community Resources | Consulting Costs-Other Improve | WALKER CONSULTANTS INC | Civic Center - Plaza and | | 8/16/2012 | $2,920.00 |
Community Resources | Consulting Costs-Other Improve | CITY OF EDGEWATER | Walker Branch -Master Plan Spl | | 10/11/2012 | $4,140.00 |
Community Resources | Consulting Costs-Other Improve | RNF CONSULTANTS INC | WH-Monument Sign | | 11/5/2012 | $595.00 |
Community Resources | Consulting Costs-Other Improve | WALKER CONSULTANTS INC | Civic Center - Plaza and | | 12/20/2012 | $1,460.00 |
Community Resources | Consulting Costs-Other Improve | POST TENSIONING INST | Digital Publication | | 9/23/2013 | $28.50 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 6/4/2014 | $8,625.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | GMRC Pickleball Court Services | | 6/10/2014 | $364.00 |
Community Resources | Consulting Costs-Other Improve | BARKER RINKER SEACAT ARCHITECTURE | Link Recreation Center Aquatic | | 6/12/2014 | $22,875.88 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Add'l SOW okay per RW | | 7/9/2014 | $6,700.00 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 7/9/2014 | $8,312.50 |
Community Resources | Consulting Costs-Other Improve | BARKER RINKER SEACAT ARCHITECTURE | Link Recreation Center Aquatic | | 7/17/2014 | $7,799.44 |
Community Resources | Consulting Costs-Other Improve | WEST METRO FIRE PROTECTIO | Fire Dept Plan Review Tennis H | | 7/23/2014 | $50.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | GMRC - Concrete Sampling | | 7/23/2014 | $662.00 |
Community Resources | Consulting Costs-Other Improve | KRW CONSULTING INC | Bear Creek Lake Park Gasline | | 7/23/2014 | $665.00 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Add'l SOW okay per RW | | 8/6/2014 | $9,750.00 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 8/14/2014 | $8,250.00 |
Community Resources | Consulting Costs-Other Improve | BARKER RINKER SEACAT ARCHITECTURE | Link Recreation Center Aquatic | | 8/20/2014 | $5,914.68 |
Community Resources | Consulting Costs-Other Improve | BARKER RINKER SEACAT ARCHITECTURE | Reimburseable expenses add'l | | 8/20/2014 | $2,407.05 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 9/4/2014 | $3,687.50 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | GMRC-Tennis & Pickleball Court | | 9/18/2014 | $520.00 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 10/15/2014 | $637.88 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Add'l SOW okay per RW | | 10/21/2014 | $3,550.00 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Change Order 2 Reconf. kitchen | | 10/21/2014 | $1,550.00 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 11/5/2014 | $2,687.50 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Change Order 2 Reconf. kitchen | | 11/5/2014 | $4,150.00 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 11/13/2014 | $2,687.50 |
Community Resources | Consulting Costs-Other Improve | RNF CONSULTANTS INC | MONUMENT SIGN WH | | 12/2/2014 | $57.50 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 12/3/2014 | $787.50 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | CONCRETE SAMPLING BCLP | | 12/4/2014 | $4,703.50 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | BCLP - Concrete Sampling | | 12/23/2014 | $3,209.50 |
Community Resources | Consulting Costs-Other Improve | RNF CONSULTANTS INC | MONUMENT SIGN WH JOB 4300.0 | | 12/24/2014 | $28.75 |
Community Resources | Consulting Costs-Other Improve | JAMIE S SABBACH -- 110 PERCENT LLC | Community Resources Strategic | | 1/12/2015 | $4,462.50 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 1/13/2015 | $2,666.31 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | CONCRETE SAMPLING BCLP | | 1/26/2015 | $722.00 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 2/10/2015 | $3,896.25 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | 2014 COMPACTION TESTING | | 2/20/2015 | $4,428.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | COMPACTION TESTING BCLP | | 3/16/2015 | $454.50 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | CONCRETE SAMPLING/COMPRESSION | | 3/16/2015 | $437.50 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 4/14/2015 | $3,098.75 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Mountair Park W 14th Ave Soils | | 4/17/2015 | $796.00 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 5/14/2015 | $2,274.75 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | CONCRETE SAMPLING/BCLP | | 6/23/2015 | $667.50 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Change Order 2 Reconf. kitchen | | 7/9/2015 | $1,845.35 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 7/22/2015 | $1,093.90 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 8/6/2015 | $3,735.38 |
Community Resources | Consulting Costs-Other Improve | EJ ARCHITECTURE | Change Order 2 Reconf. kitchen | | 8/13/2015 | $1,254.65 |
Community Resources | Consulting Costs-Other Improve | ESI LAND SURVEYING LLC | PROJ 15-143 BC GREENBELT | | 9/9/2015 | $1,200.00 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 9/16/2015 | $854.70 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 9/30/2015 | $919.75 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Dry Gulch Trail - Design from | | 10/14/2015 | $3,933.63 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | COMPACTION TESTING BCLP - | | 10/22/2015 | $236.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | CONCRETE SAMPLING, COMPRESSION | | 10/22/2015 | $271.00 |
Community Resources | Consulting Costs-Other Improve | SAMS CLUB | Recreation Supplies | | 2/16/2016 | $89.28 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Project 153735 Link Rec Center | | 2/17/2016 | $814.00 |
Community Resources | Consulting Costs-Other Improve | D & M UTILITY SERVICES LLC | LHC Pothole Repair | | 4/21/2016 | $4,300.00 |
Community Resources | Consulting Costs-Other Improve | WEST METRO FIRE PROTECTIO | Small Mtce Permit Lakewood Lin | | 6/29/2016 | $75.00 |
Community Resources | Consulting Costs-Other Improve | JCPH | Jeffco County Public Health Ce | | 6/29/2016 | $81.40 |
Community Resources | Consulting Costs-Other Improve | KEN'S REPRODUCTIONS LLLP | Lakewood Link Construction Pla | | 6/29/2016 | $156.75 |
Community Resources | Consulting Costs-Other Improve | KEN'S REPRODUCTIONS LLLP | Link Drawings for CR Planning | | 7/31/2016 | $829.05 |
Community Resources | Consulting Costs-Other Improve | KEN'S REPRODUCTIONS LLLP | 2016 Construction drawings for | | 2/15/2017 | $1,973.82 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Molholm/DryGulch Trail | | 9/20/2017 | $3,673.75 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | BCLP Campground Restroom | | 10/25/2017 | $587.40 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | 2017 BCLP RESTROOM IMPROVEMENT | | 1/4/2018 | $545.00 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Molholm/DryGulch Trail | | 2/13/2018 | $530.00 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Add'l Scope of Work | | 3/13/2018 | $2,588.53 |
Community Resources | Consulting Costs-Other Improve | THE ARCHITERRA GROUP INC | Molholm/DryGulch Trail | | 4/16/2018 | $300.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Molholm Trail testing | | 7/12/2018 | $1,351.50 |
Community Resources | Consulting Costs-Other Improve | RNF CONSULTANTS INC | works done at the Link | | 7/18/2018 | $143.75 |
Community Resources | Consulting Costs-Other Improve | MOSS PHOTOGRAPHY | TAYLOR PROPERTY-18-03191 | | 9/12/2018 | $2,000.00 |
Community Resources | Consulting Costs-Other Improve | SINGLE TRACK CONSTRUCTION SERVICES LLC | Devinney & Glennon Park | | 10/4/2018 | $41,080.00 |
Community Resources | Consulting Costs-Other Improve | GROUND ENGINEERING CONSULTANTS INC | Materials Testing & Inspection | | 10/23/2018 | $1,728.50 |
Community Resources | Consulting Costs-Other Improve | GROUND ENGINEERING CONSULTANTS INC | Materials Testing & Inspection | | 10/23/2018 | $1,821.50 |
Community Resources | Consulting Costs-Other Improve | SINGLE TRACK CONSTRUCTION SERVICES LLC | Change Order 1 | | 10/30/2018 | $5,806.00 |
Community Resources | Consulting Costs-Other Improve | SINGLE TRACK CONSTRUCTION SERVICES LLC | Change Order 2 | | 10/30/2018 | $2,660.00 |
Community Resources | Consulting Costs-Other Improve | RNF CONSULTANTS INC | LINK ENTRANCE SIGN | | 11/14/2018 | $143.75 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Mount Air Park Lighting | | 11/28/2018 | $2,925.00 |
Community Resources | Consulting Costs-Other Improve | GROUND ENGINEERING CONSULTANTS INC | Materials Testing & Inspection | | 11/29/2018 | $437.50 |
Community Resources | Consulting Costs-Other Improve | SOUDER MILLER & ASSOCIATES | CLEMENTS CENTER SITE SURVEY | | 12/6/2018 | $1,650.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Mount Air Park Lighting | | 12/28/2018 | $6,165.00 |
Community Resources | Consulting Costs-Other Improve | ALM2S | Architect-Engeering Services | | 1/17/2019 | $10,588.35 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Mount Air Park Lighting | | 1/24/2019 | $2,405.00 |
Community Resources | Consulting Costs-Other Improve | RNF CONSULTANTS INC | Link Entrance Sign | | 1/25/2019 | $172.50 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Link Entrance Sign Testing | | 2/13/2019 | $1,429.00 |
Community Resources | Consulting Costs-Other Improve | ALM2S | Architect-Engeering Services | | 2/14/2019 | $3,157.52 |
Community Resources | Consulting Costs-Other Improve | MEP ENGINEERING INC | LCC Electrical Engineering | | 3/7/2019 | $4,000.00 |
Community Resources | Consulting Costs-Other Improve | MEP ENGINEERING INC | LCC Electrical Engineering | | 3/7/2019 | $4,000.00 |
Community Resources | Consulting Costs-Other Improve | ALM2S | Architect-Engeering Services | | 3/27/2019 | $2,654.00 |
Community Resources | Consulting Costs-Other Improve | SINGLE TRACK CONSTRUCTION SERVICES LLC | DIVINNEY PARK SHELTER | | 4/3/2019 | $4,080.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Link Entrance Sign Testing | | 4/4/2019 | $202.50 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Mount Air Park Lighting | | 4/10/2019 | $2,525.00 |
Community Resources | Consulting Costs-Other Improve | MEP ENGINEERING INC | LCC Electrical Engineering | | 4/15/2019 | $1,000.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Link Entrance Sign Testing | | 5/13/2019 | $174.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Mount Air Park Lighting | | 5/28/2019 | $3,050.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Mount Air Park Lighting | | 6/4/2019 | $1,730.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Additional Funds | | 6/4/2019 | $3,150.00 |
Community Resources | Consulting Costs-Other Improve | ALM2S | Architect-Engeering Services | | 6/19/2019 | $582.27 |
Community Resources | Consulting Costs-Other Improve | LYON LAND SURVEYING & MAPPING LTD | Survey Addenbrooke Fitness | | 6/26/2019 | $1,800.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Additional Funds | | 8/1/2019 | $1,220.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Additional Funds | | 9/5/2019 | $1,830.00 |
Community Resources | Consulting Costs-Other Improve | MEP ENGINEERING INC | LCC Electrical Engineering | | 9/24/2019 | $14,000.00 |
Community Resources | Consulting Costs-Other Improve | A G WASSENAAR INC | Westland Park Ped Bridge | | 12/5/2019 | $1,900.00 |
Community Resources | Consulting Costs-Other Improve | ALM2S | CO#1 Arch-Eng. Svces RR Park | | 12/5/2019 | $1,256.15 |
Community Resources | Consulting Costs-Other Improve | UPBEAT INC | Addenbrooke Park Bike Rack | | 12/13/2019 | $657.04 |
Community Resources | Consulting Costs-Other Improve | ALM2S | Architect-Engeering Services | | 12/26/2019 | $2.10 |
Community Resources | Consulting Costs-Other Improve | ALM2S | CO#1 Arch-Eng. Svces RR Park | | 12/26/2019 | $5,000.00 |
Community Resources | Consulting Costs-Other Improve | CATOR RUMA & ASSOCIATES CO | Restore PO balance | | 12/26/2019 | $1,250.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Eng. Design Services - Daniels | | 1/9/2020 | $1,228.50 |
Community Resources | Consulting Costs-Other Improve | WEST METRO FIRE PROTECTIO | Ray Ross Plan Review | | 2/12/2020 | $112.50 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Eng. Design Services - Daniels | | 2/13/2020 | $974.75 |
Community Resources | Consulting Costs-Other Improve | ALM2S | Architect-Engeering Services | | 3/3/2020 | $123.90 |
Community Resources | Consulting Costs-Other Improve | ALM2S | CO#1 Arch-Eng. Svces RR Park | | 3/3/2020 | $5,000.00 |
Community Resources | Consulting Costs-Other Improve | MULLER ENGINEERING CO INC | Eng. Design Services - Daniels | | 3/5/2020 | $8,144.00 |